1. 10 Apr, 2014 3 commits
  2. 09 Apr, 2014 3 commits
  3. 08 Apr, 2014 5 commits
  4. 07 Apr, 2014 4 commits
  5. 05 Apr, 2014 1 commit
  6. 04 Apr, 2014 3 commits
  7. 03 Apr, 2014 5 commits
    • Danny Auble's avatar
      Fix issue where associations weren't correct if backup takes control and · 9368ff2d
      Danny Auble authored
      new associations were added since it was started.
      9368ff2d
    • Morris Jette's avatar
      Permit root to raise hard limits · 9293cbf2
      Morris Jette authored
      Permit user root to propagate resource limits higher than the hard limit
      slurmd has on that compute node has (i.e. raise both current and maximum
      limits).
      bug 674674674674674674
      9293cbf2
    • Morris Jette's avatar
      Defer scheduling for many batch jobs · 57fa06bb
      Morris Jette authored
      Permit multiple batch job submissions to be made for each run of the
      scheduler logic if the job submissions occur at the nearly same time.
      bug 616
      57fa06bb
    • Morris Jette's avatar
      launch/poe - fix network value · 01fecf4d
      Morris Jette authored
      if an job step's network value is set by poe, either by directly
      executing poe or srun launching poe, that value was not being
      propagated to the job step creation RPC and the network was not
      being set up for the proper protocol (e.g. mpi, lapi, pami, etc.).
      The previous logic would only work if the srun execute line
      explicitly set the protocol using the --network option.
      01fecf4d
    • Morris Jette's avatar
      Defer scheduling for many batch jobs · dd4aa1c3
      Morris Jette authored
      Permit multiple batch job submissions to be made for each run of the
      scheduler logic if the job submissions occur at the nearly same time.
      bug 616
      dd4aa1c3
  8. 02 Apr, 2014 2 commits
    • David Bigagli's avatar
      Update NEWS and squeue man page. · 247c3ce0
      David Bigagli authored
      247c3ce0
    • Morris Jette's avatar
      launch/poe - fix network value · ad7100b8
      Morris Jette authored
      if an job step's network value is set by poe, either by directly
      executing poe or srun launching poe, that value was not being
      propagated to the job step creation RPC and the network was not
      being set up for the proper protocol (e.g. mpi, lapi, pami, etc.).
      The previous logic would only work if the srun execute line
      explicitly set the protocol using the --network option.
      ad7100b8
  9. 31 Mar, 2014 2 commits
  10. 28 Mar, 2014 3 commits
  11. 27 Mar, 2014 3 commits
  12. 26 Mar, 2014 2 commits
  13. 25 Mar, 2014 2 commits
  14. 24 Mar, 2014 2 commits